1. Initial Investment Cost  
While the most visible, this should never be the sole deciding factor.  
- Core Equipment:Includes shredders, crushers, washing systems, pelletizers, and extruders.  
- Auxiliary Systems:Covers controls (PLC), water circulation, compressed air, dust removal, and other essential subsystems.  
- Supplier Value:Established brands often justify higher initial costs through proven reliability, advanced technology, and stronger after-sales support, leading to better long-term value.  
- Key Question:Does the quoted price reflect the equipment’s technological maturity, build quality, and included ancillary systems?

2.Energy Consumption
Energy often represents the largest ongoing operational expense.  
- Power Demand:Total connected load of motors, especially in size-reduction and extrusion stages.  
- Efficiency Features:Technologies such as variable-frequency drives, high-efficiency heaters, and optimized thermal design can reduce energy use by 15–30%.  
- Process Integration:Well-designed heat recovery and closed-loop water systems minimize waste.  
- Key Question:Can the supplier provide verified energy consumption data (e.g., kWh per ton of output) for accurate operating cost projections?

3.Maintenance and Repair Expenses
Proactive maintenance is far more economical than reactive repairs.  
- Scheduled Maintenance:Includes lubrication, filter changes, wear-part inspection, and system cleaning.  
- Unscheduled Repairs:Failures cause costly emergency interventions. Equipment robustness and intelligent design directly influence this cost.  
- Serviceability:Modular layouts and easy access to critical components reduce labor time and costs.  
- Key Question:Does the supplier offer a clear maintenance schedule and support? Is the equipment designed for quick, safe servicing?

4.Cost of Downtime
Often underestimated, production stoppages can severely impact profitability and customer trust.  
- Direct Loss:Lost output during downtime. Calculated as: Hourly throughput × Profit per ton × Downtime hours.  
- Indirect Impact:Includes idled labor, expedited repair fees, and potential contractual penalties.  
- Key Question:What is the equipment’s demonstrated reliability (MTBF)? What is the supplier’s guaranteed response time and spare parts availability?

5.Spare Parts and Consumables
Wear parts are inevitable; their cost and lifespan affect both cost predictability and uptime.  
- Common Wear Items:Blades, screens, bearings, seals, and filtration elements.  
- OEM vs. Generic Parts:OEM parts typically ensure compatibility and longevity, while generic alternatives may risk performance or cause secondary damage.  
- Supply Assurance:Stable long-term access to critical spares is essential to avoid extended downtime.  
- Key Question:Can I obtain a detailed spare parts list with expected lifecycles and pricing? Are key components standardized or proprietary?

6.Depreciation and Residual Value 
Depreciation accounts for the decline in asset value over time and affects financial reporting and planning.  
- Useful Life:Industry standards typically range from 8 to 15 years, depending on equipment type and duty.  
- End-of-Life Value:The estimated resale or scrap value after the service period.  
- Calculation Example:(Initial Cost − Residual Value) ÷ Useful Life (years).  
- Key Question:Will the equipment’s design and technology remain productive and relevant throughout its expected service life?

7. Transport, Installation, and Commissioning 
These one-time costs can be significant, especially for large or complex lines.  
- Logistics:Includes freight, insurance, and onsite offloading/positioning.  
- Installation & Setup:Covers foundation work, mechanical assembly, utility connections, and system calibration.  
- Training:Initial operational and safety training for plant personnel.  
- Key Question:Does the proposal clearly itemize delivery, installation, and commissioning? What is the projected timeline from delivery to full operation?

IV. A Practical TCO Comparison Tool
To visually compare alternatives, we recommend building a TCO Evaluation Matrix covering a 5–10 year period.


Cost Category Supplier A Plan Supplier B Plan Notes
Initial Investment     ¥1,500,000 ¥1,200,000 Total price for the complete recycling line
Estimated Annual Energy Cost ¥300,000 ¥400,000 Based on annual output of 3,000 tons and electricity price of ¥0.8/kWh
Annual Maintenance & Parts ¥50,000 ¥80,000 Estimates provided by the supplier
Estimated Downtime Cost (Annual) ¥20,000 ¥60,000 Assumed downtime: Plan A – 10 hours/year; Plan B – 30 hours/year
Annual Parts Replacement ¥40,000 ¥55,000 Based on list of vulnerable parts and expected service life
Annual Depreciation Cost ¥100,000 ¥80,000 Straight-line depreciation over 10 years with zero residual value
One-Time Shipping Fee ¥80,000 ¥70,000 Included in the quoted price
Annual Total Operating Cost (2+3+4+5+6) ¥510,000 ¥675,000 Sum of annual energy, maintenance, downtime, parts replacement, and depreciation costs
5-Year Total Cost of Ownership (TCO) ¥4,130,000 ¥4,645,000 Conclusion: Although Supplier B’s initial cost is lower, its higher operating expenses result in a ¥515,000 higher total cost over 5 years compared to Supplier A.

A disciplined TCO analysis reveals the truly cost-effective choice, prioritizing long-term efficiency over initial price. For a reliable partner in building a profitable recycling operation, consider RAYFON EST MACHINERY.